As part of the work required for the RPLC DEEP CONVERSION PROJECT, a plan was made in order to hold more than 800 packages of heavy materials including containers, piping, rotating equipment, hydraulic equipment and static equipment.
5000 tons of material was estimated to be moved and placed in an area specially prepared to work day and night for two weeks.