LIFTING STORM

LIFTING STORM

As part of the work required for the  RPLC DEEP CONVERSION PROJECT, a plan was made in order to hold more than 800 packages of heavy materials including containers, piping, rotating equipment, hydraulic equipment and static equipment.



5000 tons of material was estimated to be moved and placed in an area specially prepared to work day and night for two weeks.



The materials were unloaded at the port of Guanta, Puerto La Cruz and moved overland to the refinery.


This is where I began my work, this time in his role as resident engineer.


Here are some pictures of the preparations and hosting teams as proof of my experience in this work.
 


Cranes used for lifting operations:



 





Hydraulic Crawler Cranes 7055 / 120 TON 






 

TADANO GR-600 XL/ HYDRAULIC CRANE 60 TON  





 




HIDRAULIC CRANE TREX 30 TON RT230-1






Crawler Crane set up and transportation:





WORKING IN NIGHT SHIFT