I will share to you how I carried out the inspection and repair of the pre heater furnace of train 1 and I will explain the methodology that applied to achieving my objectives.
I began to work on this project in 5th April to 15th April 2005. I worked
on this for ten days.
I was in rol as “INSPECTION CORDINATOR/ SHUT DOWN” in ORINOCO IRON COMPANY
I was in rol as “INSPECTION CORDINATOR/ SHUT DOWN” in ORINOCO IRON COMPANY
It was a repair project. I did it As a part of the activities programmed for
the shut down #08 of the train 1 Modulo #2, I proceeded to carry out the inspection
routines and the fixtures in the pre heater furnace pipes.
The objective of the project was to inspect and repair
the pre heater furnace pipes of the convection
zone, gas plant train “1 modulo #2 of Orinoco-Iron to assure the
dependability of this equipment in avoiding unprogrammed shut downs, following
the norms of manufacture for pressure
equipments (ASTM section 8, ASME B31.3 and National board Inspection code)
My position at that moment inside the organization was
“INSPECTION COORDINATOR/ SHUT DOWNS” . My mission was to execute and to drive
the mechanical inspections and tests of equipments, during the intervention of
the trains (shut downs), in order to outline recommendations and/or mechanical
modifications that guarantee greater readiness of the equipments, following the
limits of the superintendence fulfilling the norms as regards to enviroment and
security. See the follow diagram:
Diagram of Positions. I am highlighted in green
My main duties were the following:
- Basic job duties:
- Take advantage of the opportunity to
thoroughly inspect the mechanical equipment during the shut downs.
- To ensure
the dependability of the inspection of the repaired parts following the
manufactures technical specifications.
- To inspect
the works carried out by third parties.
- Technical
information of the state of the equipment during the shut downs.
- To follow
the official norms on environmental health an safety
- System of
quality ISO 9001:2000 implanted and maintained.
- Assigned
resources preserved against loss, deterioration and waste.
- Operative duties
- To
perform the reliable inspection of the mechanical maintenance.
- To
recommend high quality information which contributes to decision-making.
- Recommendations
over improvements of equipment during the shut down of trains according to technical
specifications.
- Interface
with the units involved with quality control
- To
make confidential the access information to third parties.
- Program
of daily activities executed according to that planned.
- Identify deviations and correct them in time.
The area of
the work was the gas plant, it is the area of production where natural gas is
processed to transform it in a gas reducer, using furnace reformers, pre-heater
furnace, re-boilers, absorber Column regenerator
Column, chemical
solutions, vapor, etc. and other equipment that is used in a gas plant.
The gas
reducer is used to make the reduction of the mineral. This contains 29.7 ppm
h2s, 5.6% CO, 2.9% CO2, 16.7% CH4, 66.1% h2 and 8.9%N2. this gas is preheated
in the pre heater furnace. The gas enters with a temperature of 77 °C and it
leaves toward the reactors to 832 °C.
The
reducing furnace is a cylindrical type with vertical coils and it is
constituted by the following parts: inlet header, out let header, convection
area and radiation area.
The inlet
header takes charge of to receiving the gas reducer from the gas plant and to
feed it to the convection area.
The
convection area is an enclosed chamber which holds a group of finned tubes which take charge of getting up the
temperature of the gas reducer from 77°C to 455°C before entering the radiation
area.
The
radiation area is an enclosed chamber that contains some coils of tubes made of
a very special material and inthere the biggest quantity in heat is transferred
because they are as near as possible to
some burners. The transmission of heat is given by radiation. This area
elevates the temperature of the gas to 832°C.
The coils
are configured so that the gas makes a journey sufficiently long so that it
reaches the wanted temperatures. They form three lines, these they are:
entrance line, where the gas enters from the convection area, central line and
exit line to the out let header. The following outline exemplifies the
explained above.
The out let
header takes charge of receiving of all the gas at 832°C from the radiation
area and to address it towards the area of the reactors.
Parts of the furnace. 1: inlet header, 2: outlet
header, 3: tube coils
As part of
my work list, I have a lot of experience in the inspection and repairing of
these types of furnaces, especially those of the radiation area that are those
that are exposed to the most severe conditions of pressure and temperature.
The tubes
of the radiation area are manufactured of a very special resistant material to
the high temperatures of up to 1200°C without melting. This material is the
A297 HP nb.
I will relate how I carried out the inspection and repair of the pre
heater furnace of train 1, for I will explain the methodology that applied to
achieving my objectives:
1) I
carried out the plan of inspection of the tubes taking into account the record
of them, taking in care the respective norms.
2) I
carried out the decision making regarding the repairs to be done after
interpreting all the obtained data of the non destructive testing.
3) I
coordinated, inspected and approved all the works carried out to repair the
damaged tubes, assuring the dependability, readiness and operability of the
equipment.
It is necessary to highlight the levels of
knowledge and professionalism, which have to have to inspect and repair these
tubes, are very high.
The norms of quality for the production are very strict and the good application of them maintains the security of many human lives because the very inflammable gas is managed at 211913m3n/h to 12 bar of pressure and 832 °C. The knowledge and handling of the engineering techniques is very important, not only in the productive part, but also in the moral aspect.
As a part of the inspection plan I applied eddy current inspection to the coil tubes involving all parts of the pipes including the elbows to detect corrosion. There is a type of corrosion that is very dangerous called metal dusting. Metal dusting is a destructive form of carburisation which occurs in pipes which drives gases with a carbon activity >1, in the temperature range 400 – 900 deg C. The eddy current can detect carburisation so metal dusting too.
To have a
good reference, the three files pipes were marked using numbers and
letters each like its shown next:
Example how one of the pipe files
are market. The pipes are 4” nominal diameter.
During the eddy
current test I found four pipes with high indication of carburisation. They were:
Center
line:
Level 0:, 6
B, 8 B, 10 B and 11B
To verify
the wall thickness in the section tubes with high indication, I used a
thickness test, using ultrasonic equipment. The ultrasonic equipment is able to
take very exact measurement of thickness using ultrasonic waves which go
straight through the metal and bounce to the end of the other side of the wall. The equipment interprets the bounce of the wave face and
translate it to distance or wall thickness.
During the
Thickness test I found that the four pipes with high indication of carburisation had low wall thickness. The wall
thickness of these was 10 mm and the minimum wall thickness allowed was 5,6
millimetres. I found thickness up to 4,9 mm in scanned areas.
Finally I
used an X rays test in the low thickness areas of the pipes, detecting and
verifying that the problem found was metal dusting, as I suspected. In the
fallowing image we can see the pipe # 6B.
Localized metal dusting
To repair it I did not have to cut off all the pipe, because the metal dusting was
very localized just around the weld between the bend pipe and the straight
pipe. I had to cut off
only 300 mm from the weld to
change only the damage parts of the pipes with metal dusting and weld it
again using a new pipe part.
Due to the exposure at high service temperatures secondary carbides are
formed and ductility material decreases.
This increases the risk of cracking when repairing. The following
diagram, shows the method I used to repair
the damage pipes following ASME B31-3. It is considerate like
alternative procedures,
because I had to weld new pipe parts with old pipe parts.
Method
following reference codes
Before any weld process, I preheated
the old material to 250 °C and sustain the temperature between 150 and 200°, to
avoid cracks due thermal shock. A
welding procedure was done to keep all the essentials variables under control.
During the repairing, I used Spot Check
and X ray test to certify the quality of the welding. The welds have to be
discontinuities and defects free following the reference code ASME SEC B31-3.
Once all the
repairing was finished, a leak test was done and no leaks were found. The
furnace started without any problem and is still working. No accidents
occurred.
- My view of
the overall project
When the furnace repair was done,
the quality of the welds and materials had to be the best. No mistake could be
allowed because the minimum could cause a fatal accident. The minimum leak
during running meant a certain shut down. It could became a very high losses of
money too. The repair done by me was excellent, and I felt calm because I knew
the people (workers) were safe.
- How the
project fared in meeting the goals/ requirements
After the furnace was repaired, it
was started up without any problems, no accidents, no leaks, etc, and it is still
working.
- How my
personal role contributed to the project
The fact that
I detected metal dusting problems and I repaired the furnace on time, implied
that I guaranteed the dependability of the pre heater furnace reliable and in
time. and this was one of my roles.
To see more of my competences please download my "Competency Demostration Report" pdf clicking here:
COMPETENCY DEMOSTRATION REPORT |
This comment has been removed by the author.
ReplyDeleteHi dear redears,
ReplyDeleteHeadshop Head Quarter is an online head shop that sells high quality water pipes to smokers across America. Our selection for sale include various styles of different smoking pipes, such as: scientific glass, oil rigs, dab rigs, glass on glass waterpipes, acrylic smoking pipes, bubblers, and glass water pipes. If you want to know more details about high quality glass water pipes you can see from here.Look about-high quality glass water pipes
Thanks a lot
Olivia sarah
Very great article. It helps me understanding repair and inspection of a gas furnace.
ReplyDeleteHeating and Cooling Concord
Thanks for sharing
ReplyDeleteHeating and Cooling Brampton
Thanks for sharing this effective and useful article with us.
ReplyDeleteHeating and Air Conditioning Etobicoke
Great post i read your article is superb.
ReplyDeleteHeating and Cooling Toronto
I am unable to read articles online very often, but I’m glad I did today. This is very well written and your points are well-expressed. Please, don’t ever stop writing. emergency furnace repairs
ReplyDeleteVery great article. It helps me understanding repair and inspection of a gas furnace.
ReplyDeleteFurnace Prices Calgary