This is my first job abroad, motivated by new challenges,
innovative technology, and achieving results.
The
goal of this project is to replace and install oil and gas equipments in order to
get the rehabilitation and modernization of the110,000-b/d Esmeraldas refinery that will require intermittent periods of suspended operations at the plant.
The rehabilitation and modernization project began on July 12 2014, with
operations of unidentified processing units temporary suspended to begin maintenance work on infrastructure within the refining complex.
The rehabilitation of the Esmeraldas refinery aims to equip the plant to
operate at 100% of its nameplate operational and production capacity as
well as increase its environmental performance by reducing emissions
levels that conform to national and international standards, according
to an Apr. 18 release from Ecuador’s Ministry of Non-Renewable
Hydrocarbons. Read more.