I will share to you how I carried out the inspection and repair of the pre heater furnace of train 1 and I will explain the methodology that applied to achieving my objectives.
I began to work on this project in 5th April to 15th April 2005. I worked
on this for ten days.
I was in rol as “INSPECTION CORDINATOR/ SHUT DOWN” in ORINOCO IRON COMPANY
I was in rol as “INSPECTION CORDINATOR/ SHUT DOWN” in ORINOCO IRON COMPANY
It was a repair project. I did it As a part of the activities programmed for
the shut down #08 of the train 1 Modulo #2, I proceeded to carry out the inspection
routines and the fixtures in the pre heater furnace pipes.